Liens and lien priority

Lesson 12 of 70 · All lessons · Up next: Air, surface, subsurface, and water rights →

A claim against property

A lien is a claim against property that secures payment of an obligation. It is an encumbrance, not ownership or a right to occupy. An easement is also an encumbrance, but it authorizes a use rather than securing a debt.

Classify on two axes

A voluntary lien arises by agreement, such as a mortgage or deed of trust securing a loan. An involuntary lien arises through law, such as a property tax lien, a perfected mechanic's lien for qualifying unpaid construction work, or a properly established judgment lien. Specific liens burden identified property: a mortgage, a property tax lien on a parcel, and a mechanic's lien on the improved property are examples. A general lien reaches the debtor's property within its legally defined scope; a judgment lien is the usual exam example. General does not mean that exempt property becomes available to creditors.

Rank before distributing

Priority determines which competing claims are paid first from available proceeds. Start with the usual first-in-time rule, often evaluated through recording, then check statutory priority and agreements changing rank. Property tax liens commonly outrank earlier mortgages. A subordination agreement moves the consenting lienholder behind another claim; it does not release the debt. A release removes the lien rather than moving its position.

Three boxes show the method: identify each lien's origin and scope, rank claims using dates, statutory rules and subordination, then distribute proceeds. In the example, one hundred fifty thousand dollars is available after expenses and superior claims. The senior mortgage receives one hundred twenty thousand dollars. The junior mortgage receives thirty thousand of its fifty thousand dollar claim, leaving twenty thousand unpaid. The owner receives nothing.
Classify, rank, then distribute available proceeds.

If $150,000 is available for lienholders after expenses and superior claims, a $120,000 senior mortgage receives $120,000 and a $50,000 junior mortgage receives $30,000. No funds remain for the owner. The junior claim has a $20,000 unpaid balance; personal liability is a separate question.

Recognize exceptions

Actual priority and enforcement depend on governing law, perfection, exemptions, and the instruments involved. Texas illustrates why recording order is a starting point rather than a complete answer. Texas Tax Code section 32.05 gives chapter 32 property tax liens priority over earlier mortgage and association liens, subject to stated exceptions. Section 32.04 gives these Texas tax liens equal priority among themselves and defers to federal law for competing federal tax liens.

For Texas construction liens governed by Property Code section 53.124(a) and (b), inception generally relates to visible commencement of construction or visible delivery of materials. Section 53.124(e) supplies exceptions. Section 53.122 generally places perfected mechanic's liens on equal footing, subject to its exceptions, with proportionate distribution when funds are insufficient. Do not rank all construction claims by affidavit filing date or assume every mechanic's lien defeats an earlier mortgage.

Key terms

Sample questions

What is the defining function of a real estate lien?

  • To convey ownership of the property
  • To authorize a particular use of another's land
  • To secure payment of an obligation with property
  • To restrict future building designs
Preview

This is a preview. The full lesson and question set require an active plan.